BIM Benefit Estimate (discounted cash flow)
Each saving is applied to its correct base, net of overlap, and discounted to present value.
Project parameters
The rest is land, consultancy, equipment, contingency, tax
Construction cost: 70.00 bn · BIM cost: 1.50 bn
Construction-phase assumptions
Clash-driven rework is already counted under clash — this removes the double count
Site overheads, management, equipment hire. Materials do NOT get cheaper when you build faster.
Operation & finance assumptions
Data updates, software renewal, training. Ignoring it treats O&M savings as free money.
Money saved in year 20 is not worth the same as money saved today
Results (present value)
PV of benefits
3.62 bn
PV of costs
2.32 bn
Net present value
1.30 bn
ROI (on PV basis)
56%
Discounted payback: 1.0 years
Nominal totals (undiscounted): benefits 5.41 bn, costs 3.50 bn
Cumulative discounted cash flow (bn VNĐ)
Crossing the zero line is the payback point
Components (nominal, bn VNĐ)
Benchmark figures — source-labelled
Clash detection savings
Reduction in design conflict detection & resolution costs during construction
Rework reduction
Reduction in design error corrections during construction vs traditional CAD
Schedule reduction (4D)
Construction duration reduction through 4D scheduling and early coordination. Note: this is a % of TIME — it only saves the time-dependent share of cost.
O&M savings (AIM)
Operational cost reduction through accurate AIM data and integrated CMMS