B
BIMKit
All BIM Uses
Pre-Construction / TenderingIn depth

Phase Planning (4D)

Mô phỏng tiến độ (4D)

Link the 3D model with schedule data (WBS) to visually simulate the construction sequence, detect schedule conflicts, and optimize construction methodology.

Common tools

Revit, Navisworks TimeLiner, Forma Data Management

Value delivered

Common at major Vietnamese contractors; required in many international tenders

Adoption in Vietnam

Gained traction in Vietnam from 2018–2020 driven by FDI projects and industrial zone requirements.

Level of Information Need (LOIN)

G = Geometry · A = Alphanumeric · D = Documentation (ISO 7817-1:2024 method). A blank cell means this use sets no specific requirement for that discipline/stage.

DisciplineConceptSchematicDevelopedTechnicalAs-built / Operation
ArchitectureG2·A1·D0G3·A1·D0G3·A2·D1
StructureG2·A1·D0G3·A1·D0G3·A2·D1
MechanicalG3·A1·D0
ElectricalG3·A1·D0
PlumbingG3·A1·D0

Critical stages: Schematic · Developed · Technical

Rationale: 4D = geometry + time. Primary structural/arch elements drive sequence visualisation; G2→G3 as the WBS firms up. A1 carries phase/status/zone attributes (Existing / Demolition / New / Temporary). A2 + D1 at ST4 link schedule and progress data. MEP enters at ST4 only for construction-phase sequencing.

What it really is

4D links 3D model objects to schedule tasks to visually simulate the construction sequence over time. Each task is mapped to a set of objects; running the simulation shows the building rising along the programme and allows planned to be compared with actual. Unlike a Gantt chart divorced from the model — where the reader must imagine the space — 4D bridges programme and model visually, exposing space–time conflicts before they reach site: two crews in the same zone, a crane path crossing an active work area. The value is not the polished video but the times the sequence had to be changed after watching it.

When to use

Worthwhile for Grade II and above works, multi-phase or congested-site projects such as high-rises, infrastructure and large FDI projects, and projects with high delay risk. Maintain the 4D model from preconstruction through to completion — built once and abandoned, it retains only presentational value.

Prerequisites

  • A coordinated model completed and through basic clash coordination
  • A construction schedule with consistent task identifiers
  • Model objects carrying identifiers or properties sufficient to build search sets linking to tasks
  • A planner skilled in both scheduling and model linking — lacking either, the 4D model will not reflect the real construction method
  • A BEP or contract defining the LOIN and 4D scope (Art. 8(2))

Inputs

REQCoordinated 3D model

Task team · .rvt / IFC / .nwc

REQConstruction schedule

Lead appointed party · .mpp / .xer / .csv

REQTask-to-object mapping rules

Lead appointed party · .xlsx

REQEIR and the LOIN for 4D

Appointing party · .pdf

OPTConstruction method statement and site layout

Lead appointed party · .pdf / .dwg

OPTBEP and responsibility matrix

Lead appointed party · .pdf

Outputs

4D model linked to the schedule

.nwdAppointing party · lead appointed party

Accepted when: Every task linked to the right objects, the simulation runs the full project lifecycle, no orphaned objects remain

Sequence simulation video

.avi / .mp4Appointing party

Accepted when: Reflects the approved phase sequence

Space–time conflict report

.pdfLead appointed party

Accepted when: Lists each conflict with its resolution, not just screenshots

Planned versus actual comparison

.nwd / .pdfLead appointed party

Accepted when: Updated against site progress at the agreed frequency

General workflow

1

Federate the coordinated model

Append discipline models into one federated model, verify the shared origin, and create cache files so the simulation runs smoothly on a large model.

Task team · lead appointed party · Navisworks ManageFederated model

2

Build or import the schedule

Build the schedule with consistent task identifiers. The industry-standard planning tools are Primavera P6 and Microsoft Project; where neither is used, TimeLiner can create and edit tasks directly.

Lead appointed party · Navisworks TimeLiner · Primavera P6 or Microsoft ProjectConstruction schedule

3

Import the schedule into TimeLiner

Add the schedule data source, map columns to the corresponding fields, then rebuild the task hierarchy to verify the import before attaching objects.

Lead appointed party · Navisworks TimeLinerImported tasks

4

Build search sets and attach tasks

Use dynamic search sets based on object properties rather than static selection sets — dynamic sets update when the model changes, static ones do not, which is the most common reason a 4D model goes stale within weeks.

Lead appointed party · Navisworks TimeLinerTask-to-object links

5

Run the simulation and review the sequence

Run the simulation to find space–time conflicts. TimeLiner can be linked to the clash tool to detect time-based clashes rather than relying on visual review alone.

Lead appointed party · Navisworks TimeLiner · Navisworks Clash DetectiveSpace–time conflict report

6

Optimise the sequence and export the simulation

Adjust the sequence and method based on what the simulation revealed, then export a video to communicate the plan to parties who cannot read a programme.

Lead appointed party · Navisworks TimeLiner4D simulation video

7

Share and track actual progress

Store the 4D model on the CDE and update actual against planned as site progresses, so the model stays useful through construction rather than ending at the approval submission.

Appointing party · lead appointed party · Forma Data Management (CDE) · Forma BuildUpdated 4D model

Diagram

Task team / BIM
1Coordinated 3D model
Lead appointed party
2Build or import schedule
3Import into TimeLiner
4Search sets and task links
5Run 4D simulation
6Export simulation video
Appointing party
7Approve the construction plan
Space–time conflict found → fix the sequence before it reaches site
Time axis
Foundations
Structure
Finishes
MEP

Site actuals feed back into the simulation to compare planned with actual

Common pitfalls

Tasks cannot be linked to any objects

Cause: Task identifiers and object properties do not follow a common convention

Fix: Standardise the coding rules and use dynamic search sets rather than static selection sets

The simulation does not reflect the real construction method

Cause: The schedule was built in isolation, without breakdown by phase and work zone

Fix: The planner works directly with the BIM team to break tasks down by zone and phase

The 4D model goes stale within weeks

Cause: Not updated when design or schedule changes, compounded by static selection sets

Fix: Manage versions on the CDE and use dynamic search sets so model changes are picked up automatically

Space–time conflicts are missed

Cause: Review relies on watching the simulation by eye

Fix: Link TimeLiner to the clash tool to detect time-based clashes

Stakeholders still do not understand the construction plan

Cause: Only a bar-chart programme was presented

Fix: Export a 4D simulation video to communicate visually with non-technical parties

Measuring effectiveness

Delay reductionAcademic

Compare delay on projects with and without 4D

Benchmark: Studies report a very wide range, from 7% to 67%. Read it as a range, not a figure: measurement methods differ substantially between studies

Reduction in project delivery time with BIMAcademic

Compare delivery time across case studies with and without BIM

Benchmark: About 20% on average in a multi-case synthesis. Note this is the effect of BIM overall, not 4D's isolated contribution

Space–time conflicts caught earlyInternal target

Count conflicts found during preconstruction through time-based clash checks

Benchmark: no independent benchmark — set an internal target

Legal basis

There is NO specific requirement for BIM-based scheduling or 4D simulation in Decree 217/2026/NĐ-CP — 4D falls under Article 8 generally. Art. 8(1)(a) makes BIM mandatory from Grade II; Art. 8(2) assigns scope, content and information requirements to the contract, the basis for bringing 4D into scope and setting the LOIN; Art. 8(4) requires a CDE to be established and operated for Grade I+ public-investment works, where the 4D model is stored and shared; Art. 8(5) allows the authority to use BIM data to support appraisal, including checking technical conflicts. Progress-tracking provisions in Decree 210/2026/NĐ-CP only encourage digital platforms rather than mandating 4D. The practical consequence: like 5D, 4D is a CONTRACTUAL obligation — if you want it, write it into the EIR and BEP.

Sources

OfficialBIM mandatory from Grade II; scope and information requirements by contract; CDE for Grade I public investment; appraisal includes technical conflict checking NĐ 217/2026/NĐ-CP, Điều 8 — Công báo Chính phủ (2026)
OfficialAppointing party, lead appointed party and task team roles in information management ISO 19650-1:2018 (2018)
AcademicSystematic review of 69 studies, 57 benefits of 4D BIM; visualisation and scheduling most frequently cited Results in Engineering (ScienceDirect) (2025)
AcademicReported delay reduction ranging from 7% to 67% Results in Engineering (ScienceDirect) (2024)
AcademicBIM adoption reduces project delivery time by about 20% on average Discover Materials (Springer), Vol. 5 (2025)
Academic4D construction planning is the BIM use with the strongest influence on delay reduction Results in Engineering (ScienceDirect) (2024)

Only official sources (legislation, standards) and peer-reviewed academic work are cited. No vendor marketing figures or press sources. Reference only — does not replace legal advice.