B
BIMKit
All BIM Uses
ConstructionIn depth

Digital Fabrication

Chế tạo sẵn / Fabrication

Extract data directly from the BIM model to drive CNC/plasma machines producing steel, precast, or MEP modules off-site in the factory — reducing field labor.

Common tools

Tekla Structures, Advance Steel, Autodesk Inventor

Value delivered

Applied on Vietnamese supertall towers for complex transfer-floor steelwork and precast components

Adoption in Vietnam

Common among Vietnamese steel contractors (PEB Steel, Zamil) and large precast projects.

Level of Information Need (LOIN)

G = Geometry · A = Alphanumeric · D = Documentation (ISO 7817-1:2024 method). A blank cell means this use sets no specific requirement for that discipline/stage.

DisciplineConceptSchematicDevelopedTechnicalAs-built / Operation
ArchitectureG4·A2·D1
StructureG4·A2·D2
MechanicalG4·A2·D1
ElectricalG4·A2·D1
PlumbingG4·A2·D1

Critical stages: Technical

Rationale: G4 (fabrication / CNC-ready, LOD400) is the defining requirement across all disciplines — shop drawings, spool sheets, precast/prefab modules are driven directly from model geometry. A2 carries manufacturer / material / connection specifications. STRU reaches D2 for mill certs / test certificates on structural steel or precast. This sets the G-ceiling at ST4.

What it really is

Digital Fabrication is the process of raising a BIM model from a design-intent Level of Information Need to a fabrication-level LOIN (per ISO 7817-1:2024), breaking it into individually tagged components (piece marks), then exporting control data directly to CNC/plasma steel-cutting machines, rebar-bending lines, or ductwork and sheet-metal forming lines in a factory — instead of workers reading paper drawings and measuring by hand. Unlike a design model, which only needs to be right in position and overall size, a fabrication model must be right down to every bolt hole, weld, fabrication tolerance and erection tolerance — a single millimetre of error here can mean a component does not fit on site. The workflow runs both ways: downstream, an approved design model flows to the shop as fabrication data; upstream, deviations measured during fabrication and erection must feed back into the model to update the as-built record, rather than stopping at a one-off file export. In Vietnam, the two areas with genuinely wide uptake are prefabricated structural steel (industrial sheds, high-rise steel frames) and prefabricated MEP (ductwork modules, pipe clusters); precast concrete fabrication and other complex-geometry fabrication remain limited, mostly confined to the small number of factories that have invested in automated lines.

When to use

Worth investing in when a project has enough structural steel or prefabricated MEP scope to offset the cost of building a fabrication model and setting up CNC data — industrial sheds, steel-framed high-rises, or projects with a high density of mechanical and electrical equipment. Start only once the design model has passed basic clash coordination and the main connection details are approved — sending an insufficiently detailed model to the shop is the most common reason a project has to redo the work.

Prerequisites

  • A design model through basic clash coordination with the main connection details approved — depends directly on Design Authoring and 3D Coordination
  • A shop or specialty subcontractor with compatible CNC equipment and software able to read model-exported data (NC1/DSTV for steel, DXF for sheet metal and ductwork)
  • A BEP or fabrication contract stating who is responsible for raising the LOIN to fabrication level — usually the specialty subcontractor, not the original design consultant (Art. 8(2))
  • Erection tolerances and the construction method already agreed among the designer, the fabrication shop and the erection crew before material is cut
  • A shop QA/QC procedure and an as-fabricated measurement plan defined before batch production starts

Inputs

REQCoordinated design model at design/construction LOIN

Design task team · .rvt / IFC

REQEIR/BEP defining the fabrication LOIN and digital fabrication scope

Appointing party · lead appointed party · .pdf / .docx

REQApproved structural connection design drawings and model

Structural engineer · .pdf / .rvt

REQApplicable material standards and fabrication tolerances (steel grade, sheet thickness, erection tolerance)

Design consultant · appointing party · .pdf

OPTTransport size/weight limits and site crane capacity

Construction contractor · .pdf / .xlsx

OPTResponsibility matrix assigning who builds the fabrication model

Lead appointed party · .pdf

Outputs

Fabrication model broken into components with piece marks

mô hình Advance Steel/gốc + IFCFabrication shop

Accepted when: Every component has a unique piece mark, matches the approved connection design, no orphaned components remain

CNC control data (NC1/DSTV, nested DXF)

.nc1 / .dxfFabrication shop

Accepted when: Loads directly into the CNC machine, no manual re-entry of dimensions

Shop and erection drawings

.pdf / .dwgFabrication shop · erection contractor

Accepted when: Complete dimensions, tolerances, weld/bolt symbols, consistent with the fabrication model

Fabrication cutting list / bill of materials

.xlsxFabrication shop · procurement

Accepted when: Matches model quantities, no double counting, traceable to individual components

Fabrication and erection tolerance report

.pdf / .xlsxLead appointed party · appointing party

Accepted when: States measured deviation against the model, the acceptance threshold, and what must be updated back into the model

General workflow

1

Freeze the design model before handover to fabrication

Verify the model has passed basic clash coordination, objects are the correct types, and the main connection details are approved. A design model and a fabrication model sit at two different LOIN levels — handing the design model straight to the shop without an enrichment step is the most common starting mistake.

BIM Coordinator · Revit · Navisworks ManageFrozen design model ready for handover to the shop

2

Enrich the fabrication model

The shop or fabrication team rebuilds objects to bolt/weld connection detail, assigns a unique piece mark to each component, and defines the fabrication method per section type. This is the step that raises the design LOIN to a fabrication LOIN — skip it and the exported CNC data is wrong from the start.

Shop fabrication engineer (fabrication task team) · Autodesk Advance Steel (Tekla Structures is also common in the industry for the same role)Fabrication model with piece marks

3

Check fabricability, transport and erection feasibility

Simulate the erection sequence, check transport size and weight limits along the real route, crane working radius, and add erection tolerance allowances into the fabrication model before material is cut.

BIM Coordinator · construction crew · Navisworks ManageApproved fabricability and transport report

4

Export CNC control data

Export NC1/DSTV data for steel cutting/drilling, or nested DXF for sheet metal and ductwork, directly from the fabrication model. Never re-enter dimensions into the machine by hand — this is the most common source of error when the model and the shop remain disconnected.

Shop fabrication engineer · Autodesk Advance Steel (NC1/DSTV export)CNC control files

5

Fabricate in the shop and run quality control

The CNC line cuts, drills and welds per the exported data. Each component is measured against the defined fabrication tolerance before packing — anything out of tolerance is held and reworked in the shop, never allowed to reach site.

Fabrication shop · In-house CNC line and QC inspection procedureQC-passed fabricated components

6

Pack, transport and erect

Pack in the sequence simulated for erection, transport and erect on site per the erection drawings. Measure the as-erected position with an electronic total station to confirm the agreed erection tolerance is met.

Erection contractor · Electronic total station and erection drawingsErected components with as-measured coordinates

7

Feed tolerance data back into the model

Compare as-measured data against the fabrication model, log the deviation, and update the model when it exceeds the agreed threshold. This is the step most often skipped, leaving the later as-built model out of step with what is actually installed on site.

BIM Coordinator · Navisworks Manage · RevitModel updated to as-fabricated state, data handed to Record Modelling

Diagram

Design task team
1Coordinated, frozen design model
Fabrication shop
2Enrich fabrication model (piece marks, connections)
3Check fabricability & transport
4Export CNC data (NC1/DSTV)
5Fabricate and QC in the shop
Erection contractor / site
6Transport and erect on site
7As-fabricated survey, confirm tolerance
Tolerance deviation over threshold → return to the fabrication model, not a manual site fix

Site measurement data must feed back to the shop and the model — this is not a one-way flow from model to shop

Common pitfalls

The shop rejects the model for lacking connection detail to fabricate from

Cause: The design-LOIN model was sent straight to the shop, mistaken for a fabrication-LOIN model

Fix: Require a separate fabrication-model enrichment step and assign responsibility clearly in the BEP before signing the fabrication contract

Components match the drawings but do not fit on site

Cause: Erection tolerance was not accounted for, so deviation accumulates across a chain of connected components

Fix: Build erection tolerance into the fabrication model and simulate erection before exporting CNC data

The design changes after handover to the shop but components are still fabricated to the old version

Cause: The fabrication model and data were fully disconnected from the source model, with no shared version control

Fix: Keep the fabrication model linked to the design model through the CDE and require production to stop on any unconfirmed change

Fabricated components cannot be transported to site

Cause: Transport size and weight limits were not checked before splitting components into modules

Fix: Check vehicle and route transport limits while building the fabrication model, before CNC data is exported

Field-measured deviations never make it back to the shop or the model

Cause: The workflow only runs one way from model to shop, with no mandatory feedback step

Fix: Make the as-fabricated survey and tolerance feedback to the model a mandatory part of the acceptance process

Measuring effectiveness

First-time-fit rate of erected componentsInternal target

Components erected correctly to tolerance on the first attempt divided by total components erected in the batch

Benchmark: no independent benchmark — set an internal target

RFIs raised after CNC data has been exportedInternal target

Count RFIs concerning the model or fabrication data raised after the CNC export milestone

Benchmark: no independent benchmark — set an internal target

Time from approved design model to CNC-ready dataInternal target

Working days from the design-freeze milestone to the NC1/DSTV export

Benchmark: no independent benchmark — set an internal target

Legal basis

There is NO specific requirement for digital fabrication in Decree 217/2026/NĐ-CP — this use falls under Article 8 generally. Art. 8(1)(a) makes BIM mandatory for new-build works Grade II and above; Art. 8(2) assigns scope, content and information requirements to the contract — the sole basis for bringing the fabrication LOIN, fabrication-model responsibility and tolerance thresholds into the EIR/BEP; Art. 8(6) requires BIM data to be managed under intellectual-property law, which matters in practice because a fabrication model (piece marks, connection detail) is often copyrighted by the specialty subcontractor and its usage rights need to be agreed at handover. The practical consequence: like 4D and 5D, digital fabrication is a CONTRACTUAL obligation — if a fabrication model at the right LOIN is wanted, it must be written into the EIR and BEP; the law does not mandate it automatically.

Sources

OfficialBIM mandatory from Grade II; scope and information requirements by contract; BIM data management under intellectual-property law NĐ 217/2026/NĐ-CP, Điều 8 — Công báo Chính phủ (2026)
OfficialConcept and method for defining the Level of Information Need, including the fabrication level ISO 7817-1:2024 (2024)
OfficialAppointing party / lead appointed party / task team roles as applied to a specialty fabrication team ISO 19650-1:2018 (2018)
AcademicIntegrating BIM with prefabrication can reduce cost, curb material waste and reduce rework — based on expert interviews and simulation, not a single improvement figure Journal of Information Technology in Construction (ITcon), Vol. 30 (2025)
AcademicA BIM-enabled MEP coordination process, from design model to a prefabrication-ready model, reduces MEP-related change orders Journal of Information Technology in Construction (ITcon), Vol. 19 (2014)

Only official sources (legislation, standards) and peer-reviewed academic work are cited. No vendor marketing figures or press sources. Reference only — does not replace legal advice.