B
BIMKit
All BIM Uses
ConstructionIn depth

Construction System Design

Thiết kế biện pháp thi công

Model formwork, scaffolding, tower cranes, and temporary structures. Use virtual mock-up to verify complex construction sequences before field deployment.

Common tools

Tekla Structures, Revit (temporary works), Navisworks

Value delivered

Critical for complex structural systems (special slabs, flat slabs, transfer floors)

Adoption in Vietnam

Applied in steel building and large precast projects. Major Vietnamese contractors use it regularly.

Level of Information Need (LOIN)

G = Geometry · A = Alphanumeric · D = Documentation (ISO 7817-1:2024 method). A blank cell means this use sets no specific requirement for that discipline/stage.

DisciplineConceptSchematicDevelopedTechnicalAs-built / Operation
ArchitectureG3·A2·D1
StructureG3·A1·D0G4·A2·D1
MechanicalG3·A2·D1
ElectricalG3·A2·D1
PlumbingG3·A2·D1

Critical stages: Developed · Technical

Rationale: Biện pháp thi công: means & methods, virtual mock-ups, formwork, falsework, shoring. STRU-led: G3 at ST3 for design concept; G4 at ST4 because temporary structures require fabrication-grade detail. A2 at ST4 for material specification and load-bearing data. Other disciplines at G3/A2 for installation-method sequencing. D1 links method statements.

What it really is

Construction System Design is the modelling of temporary works that support construction — formwork, scaffolding, shoring and bracing systems, working platforms, and specific methods such as jacking or launching systems, suspended platforms, and crane climbing frames — as BIM objects kept entirely separate from the permanent structure model. Unlike building a nice-looking 3D shape purely to illustrate a method statement, this is an engineering deliverable that must pass a load-bearing check: temporary works carry a construction load combination — fresh concrete pour load, wind, live load from workers and materials, vibration from plant — quite different from the permanent building's service loads, and the temporary system itself can lose stability under vibration or cyclic loading if its connections and anchorage are inadequate. The temporary works model must be checked for clashes against the permanent structure, MEP systems being installed, and construction plant (cranes, hoists) before anything is erected on site — fixing a clash in the model is far cheaper than dismantling and re-erecting real scaffolding. This use differs from Site Utilisation Planning (site_utilisation) — which handles crane, storage and site-office positions at the overall layout scale — and from 4D Phase Planning (phase_planning_4d) — which handles construction sequencing over time: construction_sys_design handles the structural engineering of each specific temporary system, taking inputs from both rather than duplicating their content. Because temporary works are tightly coupled to what actually happens on site and are frequently adjusted in the field, the model only has value when kept in sync with the method currently in use, not as a one-off approved drawing filed away.

When to use

Worth the modelling effort when the permanent structure is complex — long-span flat slabs, post-tensioned slabs, transfer floors, steelwork, or heavy precast elements — where the temporary shoring carries large loads and an error could cause a collapse. Also worthwhile on tall buildings needing climbing scaffolding or formwork, or on congested sites where temporary works are likely to clash with cranes and access routes. For low-rise buildings with simple structural systems, conventional field-experience methods are usually sufficient and a dedicated BIM model of the temporary works is not strictly necessary.

Prerequisites

  • A permanent structure model completed at an LOIN sufficient to determine loads, anchorage points and shoring positions for the temporary works
  • An agreed construction sequence and staging, taken from 4D Phase Planning (phase_planning_4d) rather than re-derived independently
  • Site layout data (crane positions, access routes, exclusion zones) from Site Utilisation Planning (site_utilisation)
  • A method engineer with the structural competence to design the temporary works — distinct from someone who only models the geometry
  • Manufacturer specifications for proprietary formwork or scaffolding systems where a rented or off-the-shelf system is used

Inputs

REQCoordinated permanent structure model (architecture + structure)

Design task team · .rvt / IFC

REQDesign standard and construction load combinations (fresh concrete, wind, construction live load)

Structural engineer · .pdf / .xlsx

REQEIR/BEP defining the scope and LOIN for the temporary works model

Appointing party · lead appointed party · .pdf / .docx

OPTConstruction sequence and staging from the 4D simulation

Lead appointed party · .nwd / .pdf

OPTSite layout (crane positions, storage, site access)

Lead appointed party · .dwg / .rvt

OPTSpecification catalogue for proprietary formwork/scaffolding systems

System supplier · .pdf / .dwg

Outputs

Temporary works model (formwork / scaffolding / shoring) with a structural calculation report

gốc (.rvt) + báo cáo .pdfLead appointed party · supervising engineer

Accepted when: Meets load-bearing requirements under the applicable design standard, signed by the structural engineer responsible for the calculation

Clash report between the temporary works and the permanent structure/construction plant

.pdf / .bcfSite management team

Accepted when: Lists each conflict with its resolution, not just screenshots

Method-statement drawings and the erection/dismantling sequence

.pdf / .dwgSite construction crew

Accepted when: Structural calculation signed off by the structural engineer and consistent with the agreed 4D sequence

Change log of the method statement against the approved version

.pdf / bản ghi trên CDEAppointing party · lead appointed party

Accepted when: Every field change is logged, recalculated and reflected in the model before it is applied

General workflow

1

Define the preliminary construction method

The method engineer works with the 4D planning team to fix the construction sequence by phase and zone, and identifies which type of temporary system each element needs.

Method engineer · Revit · Navisworks TimeLiner (referencing the 4D sequence)Preliminary method statement by phase

2

Model the temporary works

Build parametric objects for formwork, scaffolding, shoring and working platforms, attaching dimensions and design loads to each element — not simple massing without data.

Temporary-works modeller · Revit (temporary works modelling) · Advance Steel (steel temporary systems)Discipline-level temporary works model

3

Run the load-bearing check

Run a structural analysis of the temporary works under the construction load combination. This is the step most often skipped in practice, and the direct cause of most temporary-works collapses.

Structural engineer · Autodesk Robot Structural Analysis ProfessionalTemporary works structural calculation report

4

Check clashes against the permanent structure and plant

Load the temporary works model together with the permanent structure, MEP systems being installed, and construction plant into one federated model to detect geometric conflicts before anything is erected on site.

BIM Coordinator · Navisworks Manage (Clash Detective)Temporary works clash report

5

Approve the construction method

Submit the drawings, model and calculation report to the site manager and the safety team for sign-off before erection is allowed; keep the approval on the CDE for later reference.

Site manager · safety team · Forma Data Management (CDE) — approval workflow and audit trailSigned-off construction method statement

6

Erect and supervise on site

Erect the temporary works exactly as approved; the site supervisor checks the as-built condition against the model during erection using an inspection checklist.

Construction crew · site supervisor · Field inspection checklist (paper/digital form, not a modelling tool)Erected temporary works with an inspection record

7

Update the model when the method changes on site

Any deviation from the approved version — a different prop spacing, anchorage position, or system type — must be logged, recalculated and reflected in the model before it is applied, not built from a verbal change and documented afterwards.

Method engineer · structural engineer · Revit · Autodesk Robot Structural Analysis ProfessionalUpdated model and calculation report

Diagram

Method engineer / BIM
1Preliminary method by phase
2Model the temporary works
4Clash check vs. structure & plant
7Update when the method changes on site
Structural engineer
3Load-bearing check
Site / safety
5Approve the method
6Erect on site
Method changes on site → go back to remodel and recalculate, do not build an unapproved change

The temporary works model is a living document tied to the site, not a drawing approved once and filed away

Common pitfalls

Scaffolding or formwork deforms, settles or collapses during a concrete pour or under construction load

Cause: The temporary works were modelled only to illustrate geometry, with no structural analysis run for the real construction load combination

Fix: Require a structural calculation report signed off by the structural engineer before erection is allowed, not just a good-looking 3D model

The temporary works clash with the permanent structure, MEP being installed, or the crane's travel path during construction

Cause: The temporary works model was built in isolation, with no clash check against the permanent structure and site layout before going to site

Fix: Load the temporary works model into a federated model with the permanent structure and construction plant to detect conflicts before erection

The approved method drawings no longer match what is actually being erected on site

Cause: The method was changed verbally in the field — different prop spacing, different anchorage — without updating the model and the calculation

Fix: Require every method change to go back through calculation and model update before it is applied, with the change logged on the CDE

Work is duplicated or dropped between the teams responsible for site layout, scheduling and construction methods

Cause: The scope boundary is not defined: site_utilisation covers crane and storage positions at the layout scale, phase_planning_4d covers sequencing over time, and construction system design covers the structural engineering of each specific temporary system

Fix: State the scope boundary explicitly in the BEP and use the outputs of the other two uses as inputs, rather than remodelling them from scratch

Measuring effectiveness

Temporary-works clashes caught before erectionInternal target

Count conflicts found through model-based clash checking, compared with those only discovered on site after erection

Benchmark: no independent benchmark — set an internal target

Share of temporary-works elements with a structural calculation before erectionInternal target

Elements with a calculation report divided by the total number of temporary-works elements in scope

Benchmark: no independent benchmark — set an internal target

Time from a field change in method to the model being updatedInternal target

Measure the interval between the date a change is logged and the date the model and calculation are updated on the CDE

Benchmark: no independent benchmark — set an internal target

Legal basis

There is NO specific requirement for construction system design (formwork, scaffolding, temporary shoring) in Decree 217/2026/NĐ-CP — construction_sys_design falls under Article 8 generally, not a distinct statutory obligation. Specifically: Art. 8(1)(a) makes BIM mandatory for new-build works Grade II and above, from the feasibility-study stage; Art. 8(2) assigns scope, content and information requirements — including whether the temporary works are modelled at all, and at what LOIN — to the contract for each stage, which is the only basis for putting this requirement into the EIR/BEP. Technical responsibility for the safety of temporary works — load-bearing capacity, stability during erection and dismantling — sits under specialised occupational-safety law and structural design standards, not within Decree 217. The practical consequence: modelling the construction method is a CONTRACTUAL obligation when the appointing party or contractor chooses to do it, not a separate statutory obligation under Decree 217.

Sources

OfficialBIM mandatory from Grade II; scope and information requirements set by contract NĐ 217/2026/NĐ-CP, Điều 8 — Công báo Chính phủ (2026)
OfficialConcept and method for defining the Level of Information Need ISO 7817-1:2024 (2024)
OfficialAppointing party / lead appointed party / task team roles in information management UK BIM Framework — ISO 19650 Guidance Part 2 (2021)
AcademicThe lack of standardised BIM objects for temporary works (formwork, scaffolding) causes productivity loss during design and construction Chi, Hampson & Biggs — Proceedings of the CIB W099 International Conference, Queensland University of Technology (2012)
AcademicScaffolding is a temporary structure sensitive to vibration and cyclic loading, and can lose stability if its critical elements are not properly monitored Ramezantitkanloo, Czepiżak & Pieńko — Archives of Civil Engineering, Vol. 70, No. 4 (2024)

Only official sources (legislation, standards) and peer-reviewed academic work are cited. No vendor marketing figures or press sources. Reference only — does not replace legal advice.